NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
The NO
Answer: A,C,D
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
A NO
Answer: A,C,D
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E
Moodle’s Blended Learning model brings classroom learning experience online with its world-class LMS. It combines instructor-led training, self-paced learning and personalized mentoring to provide an immersive learning experience.
NEW QUESTION: 3
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
A. Work breakdown dictionary
B. Code of accounts
C. Work breakdown structure
D. Project scope
Answer: C
Explanation:
Explanation/Reference:
Explanation:
Answer option A is correct.
The decomposition of the project scope results in the project's work breakdown structure (WBS). The work packages of the WBS will help the project manager and team create accurate time and cost estimates.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a visual decomposition of the project scope. The project scope is taken and broken down into smaller, more manageable units. Each of these units can be broken down again and again until you define the smallest item in the WBS called the work package.
Project groups and the project's discrete work elements are defined in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option D is incorrect. This document is not a WBS dictionary. A WBS dictionary includes entries for each WBS component that briefly defines the scope or statement of the work, defines deliverables, contains a list of associated activities, and provides a list of recognized milestones to gauge progress.
Answer option B is incorrect. The project scope precedes the creation of the WBS, as it is what the WBS is based on.
Answer option C is incorrect. The code of accounts is a numbering system to identify the components of the WBS.
Reference: The Project Management Body of Knowledge, Fifth edition, Section 5.4, Page 125 Chapter: Project Charter and Scope Management Objective: Work Breakdown Structures
NEW QUESTION: 4
Which two statements are true regarding Planning Business Flows?
A. Planners ran set up automatic release rules or release orders manually as part of the plan execution.
B. Inventory Planning cannot run in the Planning Business Flows.
C. Demand and Supply Planning have to be run in separate business flows.
D. In automated plans, all release rules must be automatic.
E. You can analyze and adjust data at any stage of the process.
Answer: A,E